[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941202":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},941202,608,1,"单选题","某项目在主要风险变量的不同情况下，可能发生事件对应的财务净现值及其概率如下表所示，则该项目净现值大于或等于零的累积概率为()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","0.62",false,{"key":16,"text":17,"correct":14},"B","0.64",{"key":19,"text":20,"correct":14},"C","0.66",{"key":22,"text":23,"correct":24},"D","0.69",true,"P[NPV\u003C0]=0.31，净现值≥0 的累计概率为1-31%=69%",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]