[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941199":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},941199,608,1,"单选题","风险分析程序包括①风险对策、②风险估计、③风险评价、④风险识别等步骤。这些步骤的先后顺序是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","④-②-③-①",true,{"key":16,"text":17,"correct":18},"B","①-④-②-③",false,{"key":20,"text":21,"correct":18},"C","④-③-②-①",{"key":23,"text":24,"correct":18},"D","④-②-①-③","一、投资项目风险分析流程 包括风险识别、风险估计、风险评价与对策研究四个基本阶段。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]