[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941179":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941179,608,2,"多选题","项目敏感性分析中通常选取的不确定因素有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","计算期末残值",false,{"key":16,"text":17,"correct":18},"B","产出物价格",true,{"key":20,"text":21,"correct":18},"C","主要投入物价格",{"key":23,"text":24,"correct":18},"D","建设投资",{"key":26,"text":27,"correct":14},"E","流动资金","BCD","⒈选取不确定因素 经验表明，通常应予进行敏感性分析的因素包括建设投资、产出物价格、主要投入价格或可变成本、运营负荷、建设期以及外汇汇率等，根据项目的具体情况也可选择其他因素。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]