[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941176":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},941176,608,1,"单选题","下列有关建设项目敏感性分析的表述中，正确的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","不确定因素的变动统一用百分数表示",false,{"key":16,"text":17,"correct":14},"B","全部不确定因素要同时进行变化",{"key":19,"text":20,"correct":14},"C","效益指标最少取三个",{"key":22,"text":23,"correct":24},"D","汇率是可以选取的不确定因素",true,"",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]