[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941171":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},941171,608,1,"单选题","项目经济评价往往需要对项目的风险与不确定性进行分析。下列关于风险与不确定性的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","风险是可以量化的",false,{"key":16,"text":17,"correct":18},"B","风险是不可保险的",true,{"key":20,"text":21,"correct":14},"C","不确定性的发生概率未知",{"key":23,"text":24,"correct":14},"D","不确定性可能影响更大","选项B 错误，风险是可以保险的",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]