[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941152":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941152,608,2,"多选题","下列行为中，属于风险转移的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","签订发包合同",true,{"key":16,"text":17,"correct":18},"B","设立应急储备金",false,{"key":20,"text":21,"correct":18},"C","彻底改变项目原方案",{"key":23,"text":24,"correct":14},"D","发行股票筹集项目资金",{"key":26,"text":27,"correct":14},"E","在合同中列入免责条款","ADE","非保险转移主要有三种方式：出售、发包、免责合同。 ⑴出售。通过买卖契约将风险转移给其他单位。例如，项目可以通过发行股票或债券筹集资金。股票或债券的认购者在取得项目的一部分所有权时，也同时承担了一部分风险。 ⑵发包。发包就是通过从项目执行组织外部获得货物、工程或服务而把风险转移出去。发包时又可以在多种合同形式中选择。例如建设项目的施工合同按计价形式划分，有总价合同、单价合同和成本加酬金合同。 ⑶免责合同。在合同中列入免责条款，在某些风险事故发生时，项目班子本身不应承担责任。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]