[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941142":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941142,608,2,"多选题","阐述拟建项目社会稳定风险分析的主要结论，包括（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","社会影响分析",false,{"key":16,"text":17,"correct":18},"B","拟建项目主要的风险因素",true,{"key":20,"text":21,"correct":14},"C","社会稳定风险计划实施的监测评估",{"key":23,"text":24,"correct":18},"D","落实风险防范、化解措施的有关建议",{"key":26,"text":27,"correct":18},"E","项目稳定风险应急预案、风险管理联动机制等建议","BDE","阐述拟建项目社会稳定风险分析的主要结论，包括： ⑴拟建项目主要的风险因素； ⑵主要的风险防范、化解措施； ⑶拟建项目风险等级； ⑷落实风险防范、化解措施的有关建议； ⑸项目稳定风险应急预案、风险管理联动机制等建议。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]