[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941130":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},941130,608,1,"单选题","社会评价中的互适性分析主要是分析项目能否为当地环境所接纳以及（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","移民安置和受损补偿问题",false,{"key":16,"text":17,"correct":14},"B","项目对所在地区居民就业的影响",{"key":19,"text":20,"correct":14},"C","项目对所在地居民收入的影响",{"key":22,"text":23,"correct":24},"D","当地政府、居民支持项目的程度",true,"考点:社会互适性分析。社会互适性分析主要是分析预测项目能否为当地的社会环境、人文条件所接纳，以及当地政府、居民支持项目存在和发展的程度，考察项目与当地社会环境的相互适应关系。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]