[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941078":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941078,608,2,"多选题","项目评估质量控制的重点表现在()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","配置人力资源",true,{"key":16,"text":17,"correct":14},"B","收集待评材料",{"key":19,"text":20,"correct":14},"C","制订质量计划",{"key":22,"text":23,"correct":14},"D","建立评审制度",{"key":25,"text":26,"correct":27},"E","建立分配制度",false,"ABCD","三、项目评估质量控制的重点 ㈠配置人力资源 ㈡收集待评材料 ㈢制订质量计划 ㈣建立评审制度 ㈤建立质量控制责任制",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]