[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941064":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},941064,608,1,"单选题","政府和社会资本合作(PPP)项目物有所值评价中，政府方净成本的现值(PPP 值)与公共部门比较值(PSC 值)进行比较可对等扣除的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","有关税费",false,{"key":16,"text":17,"correct":14},"B","行政审批费用",{"key":19,"text":20,"correct":21},"C","政府自留风险的承担成本",true,{"key":23,"text":24,"correct":14},"D","可转移给社会资本的风险承担成本","3)项目全部风险成本。包括可转移给社会资本的风险承担成本和政府自留风险的承担成本，可按照上述风险承担支出的方法进行测算。其中，政府自留风险承担成本等同于PPP 值中的全生命周期风险承担支出责任，两者在PSC 值与PPP 值比较时可对等扣除。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]