[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941063":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941063,608,2,"多选题","政府和社会资本合作(PPP)项目物有所值评价中，竞争性中立调整值主要是采用政府传统投资方式比采用政府和社会资本合作(PPP)模式实施项目少支出的费用，通常包括少支出的()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","土地费用",true,{"key":16,"text":17,"correct":18},"B","建设成本",false,{"key":20,"text":21,"correct":18},"C","风险成本",{"key":23,"text":24,"correct":14},"D","有关税费",{"key":26,"text":27,"correct":14},"E","行政审批费用","ADE","2)竞争性中立调整值。主要是采用政府传统投资方式比采用PPP 模式实施项目少支出的费用，通常包括少支出的土地费用、行政审批费用、有关税费等。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]