[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941030":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941030,608,2,"多选题","政府和社会资本合作(PPP)项目物有所值评价中，政府方净成本的现值(PPP 值)等同于政府和社会资本合作(PPP)项目全生命周期内()、配套投入等各项财政支出责任的现值。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","股权投资",true,{"key":16,"text":17,"correct":14},"B","运营补贴",{"key":19,"text":20,"correct":14},"C","风险承担",{"key":22,"text":23,"correct":24},"D","财政承受能力",false,{"key":26,"text":27,"correct":24},"E","竞争性中立调整","ABC","⑴政府方净成本的现值(PPP 值)的计算 PPP 值等同于PPP 项目全生命周期内股权投资、运营补贴、风险承担和配套投入等各项财政支出责任的现值。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]