[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941014":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941014,608,2,"多选题","下列项目评估内容中，属于债权人重点关注内容的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目资源配置的合理性",false,{"key":16,"text":17,"correct":18},"B","项目融资主体的盈利能力",true,{"key":20,"text":21,"correct":14},"C","项目的技术来源",{"key":23,"text":24,"correct":14},"D","项目的社会影响",{"key":26,"text":27,"correct":18},"E","项目的偿债能力","BE","考点:项目评估的任务和原则。不同的委托主体，对评估内容及侧重点的要求可能有所不同。总体上，政府部门委托的评估项目，一般侧重于项目的经济及社会影响评价，分析论证资源配置的合理性等；银行等金融机构委托的评估项目，主要侧重于融资主体的盈利能力和偿债能力评价；企业或机构投资者委托的评估项目，将重点评估项目本身的盈利能力、资金的流动性和财务风险等方面。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]