[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940993":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},940993,608,1,"单选题","关于采用投资回收期指标进行方案评价的说法，正确的有()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","投资回收期考虑了方案整个寿命期的收益，比较客观",false,{"key":16,"text":17,"correct":14},"B","投资回收期小于基准投资回收期是项目可行的充分条件",{"key":19,"text":20,"correct":21},"C","投资回收期不能反映项目投资回收之后的情况",true,{"key":23,"text":24,"correct":14},"D","投资回收期越长，说明项目效益越好","静态投资回收期指标容易理解，计算简便，该指标在一定程度上反映了资本的周转速度，资本周转速度愈快，回收期愈短，风险愈小，盈利愈多，对于那些技术上更新迅速的项目，或资金相当短缺的项目，或未来的情况很难预测而投资者又特别关心资金补偿的项目，适宜采用投资回收期指标进行分析；但静态投资回收期指标只考虑投资回收前的经济效果，没有全面考虑方案整个计算期内的现金流量，且该指标没有考虑资金的时间价值，因此只能作为辅助评价指标，或与其他评价方法结合应用。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]