[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940988":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},940988,608,1,"单选题","下列关于项目经济评价指标的说法，正确的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","投资回收期指标是以净利润抵偿全部投资所需要的时间",false,{"key":16,"text":17,"correct":14},"B","静态投资回收期可以全面反映投资项目的经济效果",{"key":19,"text":20,"correct":14},"C","项目的净现值小于零，意味着项目出现了亏损",{"key":22,"text":23,"correct":24},"D","内部收益率不是用来计算初始投资收益的指标",true,"⒌内部收益率(IRR) 内部收益率是使投资方案在计算期内各年净现金流量的现值累计等于零时的折现率。内部收益率的经济含义是投资方案占用的尚未回收资金的获利能力，也可以看做是方案所能承受的最高贷款利率。 与净现值指标依赖于方案“外部”的基准收益率不同，内部收益率指标的确定只取决于方案“内部”的现金流量和方案计算期。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]