[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940985":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},940985,608,2,"多选题","应用净现值指标评价项目经济效果的优越性有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","能够直接反映项目单位投资的使用效率",false,{"key":16,"text":17,"correct":18},"B","能够全面考虑项目在整个计算期内的经济状况",true,{"key":20,"text":21,"correct":14},"C","能够直接说明项目运营期各年的经营成果",{"key":23,"text":24,"correct":14},"D","能够全面反映项目投资过程的收益程度",{"key":26,"text":27,"correct":18},"E","能够直接以货币额表示项目的超额盈利水平","BE","净现值指标考虑了资金的时间价值，且全面考虑了项目在整个计算期内的经济状况；经济意义明确直观，能够直接以货币额表示项目的超额盈利水平，判断直观。但该指标的计算必须首先确定一个符合经济现实的基准收益率，在项目决策过程中，由于环境因素变化和决策者及决策分析者的心理预期波动，基准收益率的确定是比较困难的。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]