[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940981":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},940981,608,1,"单选题","某项目各年的净现金流量如下表所示。该项目的静态投资回收期约为()年。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1.28",false,{"key":16,"text":17,"correct":18},"B","2.73",true,{"key":20,"text":21,"correct":14},"C","3.28",{"key":23,"text":24,"correct":14},"D","3.73","",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]