[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940975":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},940975,608,1,"单选题","下列项目可行性研究的内容中，属于建设方案主要内容是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","投资估算",false,{"key":16,"text":17,"correct":14},"B","融资计划",{"key":19,"text":20,"correct":21},"C","节能方案选择",true,{"key":23,"text":24,"correct":14},"D","费用效果分析","一般工业项目的建设方案主要包括：⑴建设规模和产品方案；⑵工艺技术及设备方案；⑶场(厂)址、线路方案；⑷原材料与能源供应方案；⑸总图运输方案；⑹土建工程方案；⑺ 公用、辅助及厂外配套工程方案；⑻节能、节水、节材方案；⑼环境生态保护方案；⑽安全、职业卫生与消防方案；⑾组织机构与人力资源配置方案；⑿项目进度计划方案等。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]