[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940968":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},940968,608,1,"单选题","关于建设项目方案研究中的原材料与燃料供应方案研究的说法，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","原材料供应应进行多方案比选",true,{"key":16,"text":17,"correct":18},"B","原材料供应必须明确、可靠",false,{"key":20,"text":21,"correct":18},"C","燃料供应只考虑生产工艺所需",{"key":23,"text":24,"correct":18},"D","利用紧缺资源可不考虑运输风险","在研究确定建设规模、产品方案、工艺技术方案的同时，要明确项目所需主要原材料和燃料的品种、数量、规格、质量的要求，对价格进行分析研究，并结合场(厂)址方案的比选确定其供应方案，A 正确。 原料来源必须明确、可靠，B 错误。 除生产工艺所需的定额外还需考虑仓储量及考虑国际政治、战争、运输等风险，C 错误。 利用紧缺资源时需考虑运输便捷性与供应的经济合理性分析，D 错误。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]