[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940944":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},940944,608,2,"多选题","建设项目整体方案的比选内容一般包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","公用工程配套设施",false,{"key":16,"text":17,"correct":18},"B","场(厂)址选择",true,{"key":20,"text":21,"correct":18},"C","建设规模与产品方案",{"key":23,"text":24,"correct":14},"D","各车间建设方案",{"key":26,"text":27,"correct":18},"E","环境保护方案","BCE","建设项目整体方案的比选内容一般包括建设规模与产品方案；总体技术路线；场址选择方案；总体布局和主要运输方案，环境保护方案；其他总体性建设方案等",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]