[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940883":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},940883,608,2,"多选题","下列关于确定投资项目建设规模所涉及因素和内容的表述中，正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","当产品市场需求量大时，应采用中、小规模",false,{"key":16,"text":17,"correct":18},"B","根据资金的可供应量，量力而行",true,{"key":20,"text":21,"correct":18},"C","尽可能使项目达到或接近合理经济规模",{"key":23,"text":24,"correct":14},"D","水利水电项目应研究资源可采储量和赋存条件",{"key":26,"text":27,"correct":18},"E","改扩建项目应研究利用现有场地和公用工程的可能性","BCE","建设规模方案的选择还应结合资金的可得性，量力而行考虑建设规模。 为达到最佳经济效益规模，应尽可能使项目达到或接近合理经济规模。 改扩建与技术改造的项目应结合利用现有场地、公用工程、辅助生产等综合因素确定建设规模。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]