[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940866":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},940866,608,2,"多选题","BOT 项目的结构包括的组织有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","项目的发起人",true,{"key":16,"text":17,"correct":14},"B","项目的投资者",{"key":19,"text":20,"correct":14},"C","项目的贷款银行",{"key":22,"text":23,"correct":24},"D","项目的设计者",false,{"key":26,"text":27,"correct":24},"E","项目的监理单位","ABC","BOT 项目的结构包括三方组织，即：项目的发起人(最终所有者)，项目的投资者和经营者，项目的贷款银行。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]