[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940846":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},940846,608,1,"单选题","在地质灾害易发区内进行工程建设，应在项目决策分析与评价阶段进行地质灾害危险性评估。地质灾害危险性评估的内容不包括()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程建设诱发地质灾害的可能性",false,{"key":16,"text":17,"correct":14},"B","对可能的地质灾害危害拟采取的防治措施",{"key":19,"text":20,"correct":14},"C","工程建设本身可能遭受地质灾害的危险性",{"key":22,"text":23,"correct":24},"D","工程建设抑制地质灾害发生的可能性",true,"",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]