[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940813":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},940813,608,1,"单选题","通常建设项目可行性研究阶段对投资估算的准确度要求(即允许误差率)为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","±5%以内",false,{"key":16,"text":17,"correct":18},"B","±10%以内",true,{"key":20,"text":21,"correct":14},"C","±15%以内",{"key":23,"text":24,"correct":14},"D","±20%以内","",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]