[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940720":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},940720,608,1,"单选题","(2013年真题) 对于政府直接投资的项目，投资主管部门需要审批()",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可行性研究报告",true,{"key":16,"text":17,"correct":18},"B","资金申请报告",false,{"key":20,"text":21,"correct":18},"C","项目申请报告",{"key":23,"text":24,"correct":18},"D","节能评估报告","本题涉及的考点是政府投资项目决策(审批)的程序。对于政府投资项目，采用直接投资和资本金注入方式的，政府投资主管部门从投资决策角度只审批项目建议书和可行性研究报告。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]