[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940708":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},940708,608,1,"单选题","（2012年真题）在项目风险管理过程中，完善项目各参与方的合同，加强合同管理，可以降低项目（ ）风险。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","自然",false,{"key":16,"text":17,"correct":14},"B","政策",{"key":19,"text":20,"correct":14},"C","社会",{"key":22,"text":23,"correct":24},"D","组织",true,"本题考查的是风险识别。完善项目各参与方的合同，加强合同管理，可以降低项目的组织风险。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]