[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940699":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},940699,608,1,"单选题","(2018年真题)项目可行性研究阶段开展社会评价的作用是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","通过对项目的社会因素进行初步的分析评价，判断项目社会可行性和可能面临的社会风险",false,{"key":16,"text":17,"correct":18},"B","将社会变量纳入项目方案的设计过程，从社会层面进行项目论证，编制社会管理方案",true,{"key":20,"text":21,"correct":14},"C","结合项目建设准备的实际情况，进一步评价项目建设面临的社会风险",{"key":23,"text":24,"correct":14},"D","重新判断项目对当地社区、人口、主要利益相关者造成的实际影响","本题考查的是项目不同阶段社会评价的工作重点。项目可行性研究（项目申请书）阶段的社会评价，这一阶段社会评价的作用是将社会变量纳入项目方案（如场址、技术的选择等）的设计过程，并从社会层面论证项目的可行性，编制社会管理、征收补偿方案等。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]