[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940657":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},940657,608,1,"单选题","(2018年真题)根据《政府和社会资本合作项目财政承受能力论证指引》，在财政承受能力评估时，政府年度财政预算支出中用于政府和社会资本合作（PPP）项目的支出与一般公共预算支出的比例上限是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5%",false,{"key":16,"text":17,"correct":18},"B","10%",true,{"key":20,"text":21,"correct":14},"C","15%",{"key":23,"text":24,"correct":14},"D","20%","本题考查的是物有所值与财政承受能力论证。每一年度全部政府和社会资本合作项目需要从预算中安排的支出责任，占一般公共预算支出比例应当不超过10%。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]