[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940648":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},940648,608,1,"单选题","(2018年真题)关于非经营性项目财务分析的说法，正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","对有营业收入的项目，应按照竞争性项目进行财务分析",false,{"key":16,"text":17,"correct":14},"B","对没有营业收入的项目，不需要考察财务可持续性",{"key":19,"text":20,"correct":14},"C","难以货币化的项目，无法进行财务分析",{"key":22,"text":23,"correct":24},"D","有营业收入的项目，其收入应优先用于支付运营维护成本",true,"本题考查的是非经营性项目。选项A，非经营性项目是非营利性的投资项目，不收费或少收费，不可按竞争性项目进行财务分析；选项B，对没有营业收入的项目，不需进行盈利能力分析，其财务分析重在考察财务可持续性；选项C，对效益难以货币化的非经营性项目，可采用效果费用比或费用效果比来进行方案比选。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]