[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940461":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},940461,607,2,"多选题","行动计划与总体规划和专项规划相比，其优点有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","更宏观",false,{"key":16,"text":17,"correct":18},"B","更具体",true,{"key":20,"text":21,"correct":18},"C","更明确",{"key":23,"text":24,"correct":14},"D","更具指导性",{"key":26,"text":27,"correct":18},"E","更具有操作性","BCE","本题考查的是发展规划期限。行动计划比总体规划和专项规划等中长期规划更明确、更具体、更具有操作性,一般包括具体目标、主要任务、责任部门等。",{"id":6,"name":31,"category":32,"favorite":33},"宏观经济政策与发展规划","建筑工程",0]