[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940454":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},940454,607,1,"单选题","简化规划中重大工程项目审批核准程序并优先保障规划选址、土地供应和融资安排，具备条件的重大工程项目不再审批（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可行性研究报告",false,{"key":16,"text":17,"correct":18},"B","项目建议书",true,{"key":20,"text":21,"correct":14},"C","项目概算书",{"key":23,"text":24,"correct":14},"D","计划任务书","本题考查的是发展规划实施。简化规划中重大工程项目审批核准程序并优先保障规划选址、土地供应和融资安排，具备条件的重大工程项目不再审批项目建议书。",{"id":6,"name":27,"category":28,"favorite":29},"宏观经济政策与发展规划","建筑工程",0]