[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940437":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},940437,607,1,"单选题","为做好总体规划的衔接工作，有关部门要积极配合规划编制部门，自收到规划草案之日起（ ）个工作日内，以书面形式向规划编制部门反馈意见。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","15",false,{"key":16,"text":17,"correct":18},"B","30",true,{"key":20,"text":21,"correct":14},"C","45",{"key":23,"text":24,"correct":14},"D","60","自收到规划草案之日起30 个工作日内，以书面形式向规划编制部门反馈意见。",{"id":6,"name":27,"category":28,"favorite":29},"宏观经济政策与发展规划","建筑工程",0]