[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940148":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},940148,607,1,"单选题","某设计单位与发包人签订了设计合同，因设计任务紧急，设计单位人员紧张，经发包人同意，将部分设计任务分包给具有相应资质条件的第三人。分包人完成的设计图纸，因设计计算错误，给发包人带来了一定的经济损失，则（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","第三人自己向发包人承担责任",false,{"key":16,"text":17,"correct":14},"B","设计单位向发包人承担责任",{"key":19,"text":20,"correct":21},"C","第三人与设计单位向发包人承担连带责任",true,{"key":23,"text":24,"correct":14},"D","发包人自己承担损失","本题考查的是合同管理制度。总承包人或者勘察、设计、施工承包人经发包人同意，可以将自己承包的部分工作交由第三人完成。第三人就其完成的工作成果与总承包人或者勘察、设计、施工承包人向发包人承担连带责任。",{"id":6,"name":27,"category":28,"favorite":29},"宏观经济政策与发展规划","建筑工程",0]