[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-940075":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},940075,607,1,"单选题","根据建设项目法人责任制，新建项目正式成立项目法人的时间要求是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","申报项目建议书时",false,{"key":16,"text":17,"correct":14},"B","项目建议书批准后",{"key":19,"text":20,"correct":14},"C","申报项目可行性研究报告时",{"key":22,"text":23,"correct":24},"D","项目可行性研究报告批准后",true,"项目可行性研究报告经批准后，正式成立项目法人。",{"id":6,"name":27,"category":28,"favorite":29},"宏观经济政策与发展规划","建筑工程",0]