[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-606-35":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":679},{"id":5,"name":6,"category":7,"favorite":8},606,"工程项目组织与管理","建筑工程",0,35,50,1948,[13,38,53,67,82,96,111,123,138,153,168,182,197,212,227,239,251,263,275,285,297,309,321,331,343,357,369,380,395,409,424,438,453,467,479,491,502,514,525,537,549,561,573,587,599,613,627,642,657,671],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":36,"analysis":37},939412,2,"多选题","根据《建设工程项目管理规范》相关规定，下列属于项目质量管理实施程序的有（ ）。",[19,23,27,30,33],{"key":20,"text":21,"correct":22},"A","确定质量计划",true,{"key":24,"text":25,"correct":26},"B","质量计划评审",false,{"key":28,"text":29,"correct":22},"C","实施质量控制",{"key":31,"text":32,"correct":22},"D","落实质量改进",{"key":34,"text":35,"correct":22},"E","开展质量检查与处置","ACDE","",{"id":39,"libraryId":5,"type":15,"typeLabel":16,"stem":40,"options":41,"answer":52,"analysis":37},939413,"根据《建设工程质量管理条例》规定，保修期最低为 2 年的工程有（ ）。",[42,44,46,48,50],{"key":20,"text":43,"correct":22},"设备安装",{"key":24,"text":45,"correct":22},"装修工程",{"key":28,"text":47,"correct":22},"排水管道",{"key":31,"text":49,"correct":26},"主体结构工程",{"key":34,"text":51,"correct":26},"屋面防水工程","ABC",{"id":54,"libraryId":5,"type":55,"typeLabel":56,"stem":57,"options":58,"answer":24,"analysis":37},939414,1,"单选题","质量特性不包括（ ）。",[59,61,63,65],{"key":20,"text":60,"correct":26},"广义性",{"key":24,"text":62,"correct":22},"永久性",{"key":28,"text":64,"correct":26},"时效性",{"key":31,"text":66,"correct":26},"相对性",{"id":68,"libraryId":5,"type":15,"typeLabel":16,"stem":69,"options":70,"answer":81,"analysis":37},939415,"关于工程项目质量及其管理的说法，正确的有（ ）。",[71,73,75,77,79],{"key":20,"text":72,"correct":22},"工程项目质量是指工程项目产品、服务满足规定要求的程度",{"key":24,"text":74,"correct":22},"工程项目质量具有时效性和相对性的特点",{"key":28,"text":76,"correct":22},"对工程项目质量的要求可以是明示的",{"key":31,"text":78,"correct":22},"人员的工作质量是工程项目质量的基础",{"key":34,"text":80,"correct":26},"工程项目质量管理的目的是建设最优质量的工程项目","ABCD",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":81,"analysis":37},939416,"质量管理的原则包括（ ）。",[86,88,90,92,94],{"key":20,"text":87,"correct":22},"关系管理",{"key":24,"text":89,"correct":22},"领导作用",{"key":28,"text":91,"correct":22},"循证决策",{"key":31,"text":93,"correct":22},"改进",{"key":34,"text":95,"correct":26},"基于历史资料的决策方法",{"id":97,"libraryId":5,"type":15,"typeLabel":16,"stem":98,"options":99,"answer":110,"analysis":37},939417,"建设单位的质量责任和义务包括（ ）。",[100,102,104,106,108],{"key":20,"text":101,"correct":22},"不得迫使承包方以低于成本的价格竞标",{"key":24,"text":103,"correct":22},"不得任意压缩合理工期",{"key":28,"text":105,"correct":26},"不得偷工减料",{"key":31,"text":107,"correct":22},"办理工程质量监督手续",{"key":34,"text":109,"correct":26},"承担质量检测","ABD",{"id":112,"libraryId":5,"type":55,"typeLabel":56,"stem":113,"options":114,"answer":28,"analysis":37},939418,"《建设工程项目管理规范》对设计质量控制规定了 5 个具体流程，第三个流程是( )。",[115,117,119,121],{"key":20,"text":116,"correct":26},"设计策划",{"key":24,"text":118,"correct":26},"设计输入",{"key":28,"text":120,"correct":22},"设计评审",{"key":31,"text":122,"correct":26},"设计输出",{"id":124,"libraryId":5,"type":15,"typeLabel":16,"stem":125,"options":126,"answer":137,"analysis":37},939419,"《工程咨询成果质量评价办法》规定，进行工业项目可行性研究报告的质量评价，应评价（ ）等方面。",[127,129,131,133,135],{"key":20,"text":128,"correct":22},"风险分析",{"key":24,"text":130,"correct":22},"多方案比选",{"key":28,"text":132,"correct":26},"社会需求",{"key":31,"text":134,"correct":22},"市场调查分析",{"key":34,"text":136,"correct":22},"贯彻宏观政策分析","ABDE",{"id":139,"libraryId":5,"type":15,"typeLabel":16,"stem":140,"options":141,"answer":152,"analysis":37},939420,"试运行阶段工程咨询单位质量管理的工作内容包括（ ）。",[142,144,146,148,150],{"key":20,"text":143,"correct":26},"编制试运行管理计划",{"key":24,"text":145,"correct":22},"督促承包方编制培训计划",{"key":28,"text":147,"correct":26},"编制试运行方案",{"key":31,"text":149,"correct":22},"考核合同目标",{"key":34,"text":151,"correct":26},"严格控制风险","BD",{"id":154,"libraryId":5,"type":15,"typeLabel":16,"stem":155,"options":156,"answer":167,"analysis":37},939421,"关于质量保修期的说法，正确的是（ ）。",[157,159,161,163,165],{"key":20,"text":158,"correct":26},"主体结构终身保修",{"key":24,"text":160,"correct":26},"屋面防水工程为2年",{"key":28,"text":162,"correct":22},"设备安装工程为2年",{"key":31,"text":164,"correct":22},"保修期自竣工验收合格之日计算",{"key":34,"text":166,"correct":26},"供热系统为2年","CD",{"id":169,"libraryId":5,"type":15,"typeLabel":16,"stem":170,"options":171,"answer":137,"analysis":37},939422,"主体结构、节能分部工程的验收参加人员包括（ ）。",[172,174,176,178,180],{"key":20,"text":173,"correct":22},"施工单位项目负责人",{"key":24,"text":175,"correct":22},"施工单位项目技术负责人",{"key":28,"text":177,"correct":26},"勘察单位项目负责人",{"key":31,"text":179,"correct":22},"施工单位技术、质量部门负责人",{"key":34,"text":181,"correct":22},"设计单位项目负责人",{"id":183,"libraryId":5,"type":15,"typeLabel":16,"stem":184,"options":185,"answer":196,"analysis":37},939423,"工程技术档案和施工管理资料包括（ ）。",[186,188,190,192,194],{"key":20,"text":187,"correct":22},"工程项目竣工报告",{"key":24,"text":189,"correct":22},"图纸会审和设计交底记录",{"key":28,"text":191,"correct":22},"设计变更通知单",{"key":31,"text":193,"correct":26},"安全事故处理记录",{"key":34,"text":195,"correct":22},"质量检验评定资料","ABCE",{"id":198,"libraryId":5,"type":15,"typeLabel":16,"stem":199,"options":200,"answer":211,"analysis":37},939424,"初步设计阶段，需报政府审批的主要技术文件包括（ ）。",[201,203,205,207,209],{"key":20,"text":202,"correct":26},"规划设计方案",{"key":24,"text":204,"correct":22},"建筑工程初步设计",{"key":28,"text":206,"correct":22},"建设工程规划许可证",{"key":31,"text":208,"correct":26},"人防规划设计",{"key":34,"text":210,"correct":26},"交通设计","BC",{"id":213,"libraryId":5,"type":15,"typeLabel":16,"stem":214,"options":215,"answer":226,"analysis":37},939425,"工程监理单位与（ ）有隶属关系或者其他利害关系的，不得承担监理业务。",[216,218,220,222,224],{"key":20,"text":217,"correct":26},"建设单位",{"key":24,"text":219,"correct":26},"设计单位",{"key":28,"text":221,"correct":22},"施工单位",{"key":31,"text":223,"correct":22},"建筑材料、建筑构配件供应单位",{"key":34,"text":225,"correct":22},"设备供货商","CDE",{"id":228,"libraryId":5,"type":55,"typeLabel":56,"stem":229,"options":230,"answer":28,"analysis":37},939426,"单位工程质量验收合格的标准不包括（ ）。",[231,233,235,237],{"key":20,"text":232,"correct":26},"所含分部工程的质量均验收合格",{"key":24,"text":234,"correct":26},"质量管理资料应完整",{"key":28,"text":236,"correct":22},"所含分部工程所有使用功能的检验资料应完整",{"key":31,"text":238,"correct":26},"观感质量应符合要求",{"id":240,"libraryId":5,"type":55,"typeLabel":56,"stem":241,"options":242,"answer":28,"analysis":37},939427,"检验批验收不包括（ ）。",[243,245,247,249],{"key":20,"text":244,"correct":26},"资料检查",{"key":24,"text":246,"correct":26},"主控项目检验",{"key":28,"text":248,"correct":22},"观感质量检查",{"key":31,"text":250,"correct":26},"一般项目检验",{"id":252,"libraryId":5,"type":55,"typeLabel":56,"stem":253,"options":254,"answer":20,"analysis":37},939428,"施工质量控制流程不包括（ ）。",[255,257,259,261],{"key":20,"text":256,"correct":22},"施工质量目标制定",{"key":24,"text":258,"correct":26},"施工质量目标分解",{"key":28,"text":260,"correct":26},"施工技术交底与工序控制",{"key":31,"text":262,"correct":26},"施工质量偏差控制",{"id":264,"libraryId":5,"type":55,"typeLabel":56,"stem":265,"options":266,"answer":28,"analysis":37},939429,"（ ）是保证各专业设计相互正确衔接的必要手段。",[267,269,271,273],{"key":20,"text":268,"correct":26},"设计接口管理",{"key":24,"text":270,"correct":26},"设计方案的审核",{"key":28,"text":272,"correct":22},"设计文件的会签",{"key":31,"text":274,"correct":26},"设计验证",{"id":276,"libraryId":5,"type":55,"typeLabel":56,"stem":277,"options":278,"answer":20,"analysis":37},939430,"针对工程设计项目建立质量目标，规定质量要求和安排应开展的活动，指的是（ ）工作。",[279,280,281,283],{"key":20,"text":116,"correct":22},{"key":24,"text":120,"correct":26},{"key":28,"text":282,"correct":26},"设计控制",{"key":31,"text":284,"correct":26},"设计管理",{"id":286,"libraryId":5,"type":55,"typeLabel":56,"stem":287,"options":288,"answer":31,"analysis":37},939431,"勘察现场作业的质量管理不包括（ ）。",[289,291,293,295],{"key":20,"text":290,"correct":26},"现场作业人员应进行专业培训",{"key":24,"text":292,"correct":26},"勘察仪器、设备、试验室有明确的管理程序",{"key":28,"text":294,"correct":26},"原始记录表格经有关作业人员检查、签字",{"key":31,"text":296,"correct":22},"工程勘察报告完整",{"id":298,"libraryId":5,"type":55,"typeLabel":56,"stem":299,"options":300,"answer":20,"analysis":37},939432,"勘察纲要应由（ ）主持编写。",[301,303,305,307],{"key":20,"text":302,"correct":22},"勘察单位项目经理",{"key":24,"text":304,"correct":26},"监理工程师",{"key":28,"text":306,"correct":26},"勘察单位技术负责人",{"key":31,"text":308,"correct":26},"总监理工程师",{"id":310,"libraryId":5,"type":55,"typeLabel":56,"stem":311,"options":312,"answer":28,"analysis":37},939433,"（ ）满足编制施工招标文件、主要设备材料订货的需要。",[313,315,317,319],{"key":20,"text":314,"correct":26},"方案设计",{"key":24,"text":316,"correct":26},"施工图设计",{"key":28,"text":318,"correct":22},"初步设计",{"key":31,"text":320,"correct":26},"技术设计",{"id":322,"libraryId":5,"type":55,"typeLabel":56,"stem":323,"options":324,"answer":20,"analysis":37},939434,"编制项目前期工作计划的同时，制订质量计划并组织实施是（ ）的职责。",[325,327,329,330],{"key":20,"text":326,"correct":22},"项目经理",{"key":24,"text":328,"correct":26},"部门经理",{"key":28,"text":326,"correct":26},{"key":31,"text":328,"correct":26},{"id":332,"libraryId":5,"type":55,"typeLabel":56,"stem":333,"options":334,"answer":28,"analysis":37},939435,"建立和实施质量管理体系的步骤中，质量管理职能分层次分解之后要做的工作是（ ）。",[335,337,339,341],{"key":20,"text":336,"correct":26},"质量目标层层分解",{"key":24,"text":338,"correct":26},"制订工程项目的质量计划",{"key":28,"text":340,"correct":22},"制订质量管理体系文件",{"key":31,"text":342,"correct":26},"按质量目标组织实施",{"id":344,"libraryId":5,"type":15,"typeLabel":16,"stem":345,"options":346,"answer":36,"analysis":37},939436,"安全教育培训应包括的步骤有（ ）。",[347,349,351,353,355],{"key":20,"text":348,"correct":22},"培训前的准备",{"key":24,"text":350,"correct":26},"安全技术交底",{"key":28,"text":352,"correct":22},"信息与知识的传授",{"key":31,"text":354,"correct":22},"培训效果评价",{"key":34,"text":356,"correct":22},"监督执行",{"id":358,"libraryId":5,"type":55,"typeLabel":56,"stem":359,"options":360,"answer":24,"analysis":37},939437,"工程项目初步设计中的安全报告的内容不包括（ ）。",[361,363,365,367],{"key":20,"text":362,"correct":26},"总平面布置",{"key":24,"text":364,"correct":22},"安全对策措施建设",{"key":28,"text":366,"correct":26},"卫生保健设施",{"key":31,"text":368,"correct":26},"地质安全影响因素",{"id":370,"libraryId":5,"type":55,"typeLabel":56,"stem":371,"options":372,"answer":20,"analysis":37},939438,"工程项目安全预评价是在工程项目的（ ）阶段开展的一项工作。",[373,375,376,378],{"key":20,"text":374,"correct":22},"可行性研究",{"key":24,"text":318,"correct":26},{"key":28,"text":377,"correct":26},"施工",{"key":31,"text":379,"correct":26},"竣工验收",{"id":381,"libraryId":5,"type":15,"typeLabel":16,"stem":382,"options":383,"answer":394,"analysis":37},939439,"工程项目施工安全计划的内容主要有（ ）。",[384,386,388,390,392],{"key":20,"text":385,"correct":26},"明确施工技术方案",{"key":24,"text":387,"correct":22},"确定安全组织机构",{"key":28,"text":389,"correct":22},"明确配置安全资源",{"key":31,"text":391,"correct":22},"制订安全技术措施",{"key":34,"text":393,"correct":22},"明确安全控制管理目标和程序","BCDE",{"id":396,"libraryId":5,"type":15,"typeLabel":16,"stem":397,"options":398,"answer":81,"analysis":37},939441,"工程项目安全预评价的方法主要有（ ）。",[399,401,403,405,407],{"key":20,"text":400,"correct":22},"因果图分析法",{"key":24,"text":402,"correct":22},"事故树分析法",{"key":28,"text":404,"correct":22},"事故模型法",{"key":31,"text":406,"correct":22},"安全度评价法",{"key":34,"text":408,"correct":26},"SWOT分析法",{"id":410,"libraryId":5,"type":15,"typeLabel":16,"stem":411,"options":412,"answer":423,"analysis":37},939442,"工程项目环境影响评价的内容主要有（ ）。",[413,415,417,419,421],{"key":20,"text":414,"correct":26},"环境资源评价",{"key":24,"text":416,"correct":22},"工程分析",{"key":28,"text":418,"correct":26},"环境保护措施评价",{"key":31,"text":420,"correct":22},"清洁生产评价",{"key":34,"text":422,"correct":22},"环境影响识别与预测","BDE",{"id":425,"libraryId":5,"type":15,"typeLabel":16,"stem":426,"options":427,"answer":52,"analysis":37},939444,"绿色设计也称为生态设计、环境设计，绿色设计的方法主要包括（ ）。",[428,430,432,434,436],{"key":20,"text":429,"correct":22},"模块化设计",{"key":24,"text":431,"correct":22},"循环设计",{"key":28,"text":433,"correct":22},"并行工程设计",{"key":31,"text":435,"correct":26},"平行工程设计",{"key":34,"text":437,"correct":26},"板块设计",{"id":439,"libraryId":5,"type":15,"typeLabel":16,"stem":440,"options":441,"answer":452,"analysis":37},939445,"绿色施工的原则包括（ ）",[442,444,446,448,450],{"key":20,"text":443,"correct":22},"关注工程项目的可持续发展，合理利用资源、能源",{"key":24,"text":445,"correct":26},"采用模块化、循环设计、并行工程设计方法",{"key":28,"text":447,"correct":22},"注重环境品质，减少施工造成的环境污染",{"key":31,"text":449,"correct":26},"建立安全施工责任制",{"key":34,"text":451,"correct":22},"结合气候、气象条件，合理安排施工计划","ACE",{"id":454,"libraryId":5,"type":15,"typeLabel":16,"stem":455,"options":456,"answer":81,"analysis":37},939446,"绿色施工是指通过科学管理和技术进步，最大限度地节约资源并减少对环境负面影响的施工活动，从而实现（ ）和环境保护。",[457,459,461,463,465],{"key":20,"text":458,"correct":22},"节能",{"key":24,"text":460,"correct":22},"节地",{"key":28,"text":462,"correct":22},"节水",{"key":31,"text":464,"correct":22},"节材",{"key":34,"text":466,"correct":26},"节电",{"id":468,"libraryId":5,"type":55,"typeLabel":56,"stem":469,"options":470,"answer":24,"analysis":37},939447,"关于绿色设计及其内容、方法的说法，正确的是（ ）。",[471,473,475,477],{"key":20,"text":472,"correct":26},"绿色设计是以工程项目全生命周期成本的最小化为目标",{"key":24,"text":474,"correct":22},"绿色设计应使所设计的产品满足绿色产品要求",{"key":28,"text":476,"correct":26},"可拆卸设计的目的是为了减少零件的种类",{"key":31,"text":478,"correct":26},"循环设计的目的是便于后期维修和降低使用成本",{"id":480,"libraryId":5,"type":55,"typeLabel":56,"stem":481,"options":482,"answer":28,"analysis":37},939448,"工程项目的绿色施工方案应包括（ ）。",[483,485,487,489],{"key":20,"text":484,"correct":26},"提高质量标准措施",{"key":24,"text":486,"correct":26},"降低成本措施",{"key":28,"text":488,"correct":22},"节地措施",{"key":31,"text":490,"correct":26},"提前竣工措施",{"id":492,"libraryId":5,"type":55,"typeLabel":56,"stem":493,"options":494,"answer":28,"analysis":37},939450,"在环境管理体系中，“信息交流”属于（ ）要素中的一项内容。",[495,496,498,500],{"key":20,"text":89,"correct":26},{"key":24,"text":497,"correct":26},"策划",{"key":28,"text":499,"correct":22},"支持",{"key":31,"text":501,"correct":26},"运行",{"id":503,"libraryId":5,"type":55,"typeLabel":56,"stem":504,"options":505,"answer":24,"analysis":37},939451,"根据《职业健康安全管理体系》，不属于运行要素的是（ ）",[506,508,510,512],{"key":20,"text":507,"correct":26},"变更管理",{"key":24,"text":509,"correct":22},"管理评审",{"key":28,"text":511,"correct":26},"外包",{"key":31,"text":513,"correct":26},"应急准备和响应",{"id":515,"libraryId":5,"type":55,"typeLabel":56,"stem":516,"options":517,"answer":31,"analysis":37},939452,"下列职业健康安全管理体系和环境管理体系要素中，不属于一级要素的是（ ）。",[518,520,522,524],{"key":20,"text":519,"correct":26},"组织所处的环境",{"key":24,"text":521,"correct":26},"领导作用与员工参与",{"key":28,"text":523,"correct":26},"绩效评价",{"key":31,"text":509,"correct":22},{"id":526,"libraryId":5,"type":55,"typeLabel":56,"stem":527,"options":528,"answer":28,"analysis":37},939453,"在职业健康安全域环境管理体系要素中，方针是以文件方式表述出职业健康安全域环境管理的（ ）。",[529,531,533,535],{"key":20,"text":530,"correct":26},"计划与规划",{"key":24,"text":532,"correct":26},"方法与手段",{"key":28,"text":534,"correct":22},"意图与原则",{"key":31,"text":536,"correct":26},"实施与运行",{"id":538,"libraryId":5,"type":55,"typeLabel":56,"stem":539,"options":540,"answer":28,"analysis":37},939454,"在环境管理体系中，由项目组织的最高管理者制订，反映环境管理意图和原则的文件是（ ）。",[541,543,545,547],{"key":20,"text":542,"correct":26},"计划文件",{"key":24,"text":544,"correct":26},"检查方案",{"key":28,"text":546,"correct":22},"环境方针",{"key":31,"text":548,"correct":26},"纠错计划",{"id":550,"libraryId":5,"type":55,"typeLabel":56,"stem":551,"options":552,"answer":31,"analysis":37},939455,"职业健康安全与环境管理体系的建立步骤中，人员培训之后的步骤是（ ）。",[553,555,557,559],{"key":20,"text":554,"correct":26},"体系策划与设计",{"key":24,"text":556,"correct":26},"成立工作小组",{"key":28,"text":558,"correct":26},"文件发布和体系试运行",{"key":31,"text":560,"correct":22},"初始评审",{"id":562,"libraryId":5,"type":55,"typeLabel":56,"stem":563,"options":564,"answer":31,"analysis":37},939456,"职业健康安全与环境管理体系整体策划和设计阶段的主要工作不包括（ ）。",[565,567,569,571],{"key":20,"text":566,"correct":26},"确定组织机构和职责",{"key":24,"text":568,"correct":26},"制订职业健康安全管理方针",{"key":28,"text":570,"correct":26},"为实施管理体系准备必要的资源",{"key":31,"text":572,"correct":22},"辨识工作场所的危险因素",{"id":574,"libraryId":5,"type":15,"typeLabel":16,"stem":575,"options":576,"answer":167,"analysis":37},939457,"进行“体系策划与设计”是建立职业健康安全与环境管理体系的工作之一，其主要内容有（ ）。",[577,579,581,583,585],{"key":20,"text":578,"correct":26},"辨识工作场所中的危险因素和环境因素",{"key":24,"text":580,"correct":26},"明确适用的职业健康安全与环境法律法规",{"key":28,"text":582,"correct":22},"制订职业健康安全（环境）管理方案",{"key":31,"text":584,"correct":22},"确定管理体系组织机构和职责",{"key":34,"text":586,"correct":26},"评价组织机构和资源配备等情况",{"id":588,"libraryId":5,"type":55,"typeLabel":56,"stem":589,"options":590,"answer":20,"analysis":37},939458,"各项生产规章制度的核心是( )。",[591,593,595,597],{"key":20,"text":592,"correct":22},"生产责任制",{"key":24,"text":594,"correct":26},"技术措施",{"key":28,"text":596,"correct":26},"职业健康措施",{"key":31,"text":598,"correct":26},"宣传教育措施",{"id":600,"libraryId":5,"type":15,"typeLabel":16,"stem":601,"options":602,"answer":226,"analysis":37},939459,"教育的内容主要包括( )。",[603,605,607,609,611],{"key":20,"text":604,"correct":26},"新技术教育",{"key":24,"text":606,"correct":26},"新结构教育",{"key":28,"text":608,"correct":22},"生产思想教育",{"key":31,"text":610,"correct":22},"职业健康技术知识教育",{"key":34,"text":612,"correct":22},"典型事故教育",{"id":614,"libraryId":5,"type":15,"typeLabel":16,"stem":615,"options":616,"answer":81,"analysis":37},939460,"生产检查的内容主要包括( )。",[617,619,621,623,625],{"key":20,"text":618,"correct":22},"查思想",{"key":24,"text":620,"correct":22},"查管理",{"key":28,"text":622,"correct":22},"查隐患",{"key":31,"text":624,"correct":22},"查整改",{"key":34,"text":626,"correct":26},"查考勤",{"id":628,"libraryId":5,"type":15,"typeLabel":16,"stem":629,"options":630,"answer":641,"analysis":37},939461,"《建设项目(工程)劳动卫生预评价管理办法》规定( )必须进行劳动卫生预 评价。",[631,633,635,637,639],{"key":20,"text":632,"correct":22},"大中型建设项目",{"key":24,"text":634,"correct":26},"火灾危险性生产类别为甲乙类的工程项目",{"key":28,"text":636,"correct":22},"爆炸危险场所等级为特别危险场所和高度危险场所的工程项目",{"key":31,"text":638,"correct":22},"大量生产或使用 I 级、Ⅱ级危害程度的职业性接触毒物的工程项目",{"key":34,"text":640,"correct":26},"大量生产或使用石棉粉料或含有 5%以上的游离二氧化硅粉料的工程项目","ACD",{"id":643,"libraryId":5,"type":15,"typeLabel":16,"stem":644,"options":645,"answer":656,"analysis":37},939462,"根据《生产事故报告和调査处理条例》，下列内容中，属于事故报告组成的有( )。",[646,648,650,652,654],{"key":20,"text":647,"correct":22},"已经采取的措施",{"key":24,"text":649,"correct":26},"事故的性质",{"key":28,"text":651,"correct":26},"事故的责任",{"key":31,"text":653,"correct":26},"事故责任者处理",{"key":34,"text":655,"correct":22},"事故的经过","AE",{"id":658,"libraryId":5,"type":15,"typeLabel":16,"stem":659,"options":660,"answer":196,"analysis":37},939463,"下列关于伤亡事故统计报告和处理制度说法正确的是( )。",[661,663,665,667,669],{"key":20,"text":662,"correct":22},"未造成人员伤亡的一般事故，县级人民政府也可委托事故发生单位组织事故调查组进行调 查",{"key":24,"text":664,"correct":22},"重大事故、较大事故、一般事故，负责事故调查的人民政府应当自收到事故调查报告之日 起 15 日内做出批复",{"key":28,"text":666,"correct":22},"特别重大事故由国务院或者国务院授权有关部门组织事故调查组进行调查",{"key":31,"text":668,"correct":26},"单位负责人接到报告后，应当于 2 小时内向事故发生地县级以上人民政府生产监督管 理部门报告",{"key":34,"text":670,"correct":22},"较大事故，是指造成 3 人以上 10 人以下死亡，或者 10 人以上 50 人以下重伤，或者 1000 万元以上 5000 万元以下直接经济损失的事故",{"id":672,"libraryId":5,"type":55,"typeLabel":56,"stem":673,"options":674,"answer":20,"analysis":37},939464,"工程项目预评价是在工程项目的( )阶段开展的一项工作。",[675,676,677,678],{"key":20,"text":374,"correct":22},{"key":24,"text":318,"correct":26},{"key":28,"text":377,"correct":26},{"key":31,"text":379,"correct":26},[680,683,686,689,692,695],{"id":55,"name":681,"category":7,"favorite":682},"领导干部任职前廉政法规知识测试题",92,{"id":684,"name":685,"category":7,"favorite":55},595,"建筑结构与设备",{"id":687,"name":688,"category":7,"favorite":55},715,"招标采购专业知识与法律法规",{"id":690,"name":691,"category":7,"favorite":55},848,"市政方向-通用基础",{"id":693,"name":694,"category":7,"favorite":8},534,"BIM工程师",{"id":696,"name":694,"category":7,"favorite":8},535]