[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-606-2":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":597},{"id":5,"name":6,"category":7,"favorite":8},606,"工程项目组织与管理","建筑工程",0,2,50,1948,[13,34,46,58,70,82,94,106,118,130,141,151,163,175,187,199,211,223,233,245,255,263,275,287,299,311,323,335,347,359,371,383,395,407,418,429,439,451,463,475,485,497,509,521,533,541,553,565,577,589],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":30,"analysis":33},937721,1,"单选题","（2016年真题）下列不属于项目分解的方法的是（ ）。",[19,23,26,29],{"key":20,"text":21,"correct":22},"A","按工作内容分解",false,{"key":24,"text":25,"correct":22},"B","按专业要素分解",{"key":27,"text":28,"correct":22},"C","按工作过程分解",{"key":30,"text":31,"correct":32},"D","按项目成本分解",true,"",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":24,"analysis":33},937722,"（2012年真题）能够清晰反映团队成员与项目相关的所有活动和同每项活动相关的所有人员的管理工具是（ ）。",[38,40,42,44],{"key":20,"text":39,"correct":22},"组织分解结构图",{"key":24,"text":41,"correct":32},"责任分配矩阵",{"key":27,"text":43,"correct":22},"资源分解结构图",{"key":30,"text":45,"correct":22},"角色—职责—职权表",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":27,"analysis":33},937723,"（2017年真题）正确评估行业和技术发展给本项目带来的影响，属于项目经理的( )。",[50,52,54,56],{"key":20,"text":51,"correct":22},"分析思维",{"key":24,"text":53,"correct":22},"信息收集",{"key":27,"text":55,"correct":32},"商业认知",{"key":30,"text":57,"correct":22},"项目决策",{"id":59,"libraryId":5,"type":15,"typeLabel":16,"stem":60,"options":61,"answer":20,"analysis":33},937724,"（2006年真题）项目团队从组建到发展起来经历的正确阶段顺序是( )。",[62,64,66,68],{"key":20,"text":63,"correct":32},"形成－磨合－规范－表现－休整",{"key":24,"text":65,"correct":22},"形成－表现－磨合－规范－休整",{"key":27,"text":67,"correct":22},"表现－磨合－形成－规范－休整",{"key":30,"text":69,"correct":22},"形成－规范－磨合－表现－休整",{"id":71,"libraryId":5,"type":15,"typeLabel":16,"stem":72,"options":73,"answer":20,"analysis":33},937725,"（2017年真题） 下列关于项目团队建设的说法，错误的是( A )",[74,76,78,80],{"key":20,"text":75,"correct":32},"团队发展的规范阶段，是团队状态最好的时期",{"key":24,"text":77,"correct":22},"团队成员间的信任，是团队合作的前提与基础",{"key":27,"text":79,"correct":22},"团队精神包括凝聚力、互信合作意识和团队士气三个层次",{"key":30,"text":81,"correct":22},"项目团队成员调整的目的是为了使团队更适合项目工作",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":20,"analysis":33},937726,"（2016年真题）项目团队实现预定目标的关键是( )。",[86,88,90,92],{"key":20,"text":87,"correct":32},"将团队作为一个完整的整体来开发",{"key":24,"text":89,"correct":22},"提高参与项目个人的贡献力",{"key":27,"text":91,"correct":22},"提高项目团队的能力",{"key":30,"text":93,"correct":22},"使团队保持和发展工作动力",{"id":95,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":97,"answer":27,"analysis":33},937727,"（2013年真题）将项目团队部分人员放到恶劣的环境中生活一段时间，让其学会相互适应。这种做法在团队能力开发中称为( )",[98,100,102,104],{"key":20,"text":99,"correct":22},"工作规程训练",{"key":24,"text":101,"correct":22},"奖惩训练",{"key":27,"text":103,"correct":32},"人员配合训练",{"key":30,"text":105,"correct":22},"团队建设训练",{"id":107,"libraryId":5,"type":15,"typeLabel":16,"stem":108,"options":109,"answer":27,"analysis":33},937728,"（2011年真题）下列工作中，不属于工程项目组织计划工作的是( )",[110,112,114,116],{"key":20,"text":111,"correct":22},"确定角色和职责",{"key":24,"text":113,"correct":22},"制订人员配备计划",{"key":27,"text":115,"correct":32},"确定项目管理模式",{"key":30,"text":117,"correct":22},"制订组织关系图",{"id":119,"libraryId":5,"type":15,"typeLabel":16,"stem":120,"options":121,"answer":30,"analysis":33},937729,"（2006年真题）在工程项目人力资源管理中，最为基础性的工作是( )。",[122,124,126,128],{"key":20,"text":123,"correct":22},"编制人员配备计划",{"key":24,"text":125,"correct":22},"编制组织关系图表",{"key":27,"text":127,"correct":22},"雇员考核",{"key":30,"text":129,"correct":32},"进行工作分析",{"id":131,"libraryId":5,"type":15,"typeLabel":16,"stem":132,"options":133,"answer":24,"analysis":33},937730,"（2009年真题）可以同时规定项目团队成员角色、职责与任务范围的管理工具是( )",[134,136,137,139],{"key":20,"text":135,"correct":22},"关键线路法",{"key":24,"text":41,"correct":32},{"key":27,"text":138,"correct":22},"组织结构图",{"key":30,"text":140,"correct":22},"工作分解结构",{"id":142,"libraryId":5,"type":15,"typeLabel":16,"stem":143,"options":144,"answer":27,"analysis":33},937731,"（2010年真题）进行工程项目组织内角色和职责安排，适宜使用的工具是( )",[145,146,148,149],{"key":20,"text":140,"correct":22},{"key":24,"text":147,"correct":22},"网络图",{"key":27,"text":41,"correct":32},{"key":30,"text":150,"correct":22},"S曲线",{"id":152,"libraryId":5,"type":15,"typeLabel":16,"stem":153,"options":154,"answer":20,"analysis":33},937732,"（2017年真题）下列关于组织结构的说法，错误的是( )。",[155,157,159,161],{"key":20,"text":156,"correct":32},"工程项目必须建立正式的详细组织关系图",{"key":24,"text":158,"correct":22},"通过组织分解结构可在每个相关部门下列出项目活动或工作包",{"key":27,"text":160,"correct":22},"组织关系图通过某种图形来确定和体现相互工作关系",{"key":30,"text":162,"correct":22},"组织分解结构图是一种特殊的组织关系图",{"id":164,"libraryId":5,"type":15,"typeLabel":16,"stem":165,"options":166,"answer":20,"analysis":33},937733,"（2006年真题）某制造厂技改工作中，要求总装车间生产能力的扩大必须与发动机生产能力相配套，这属于项目的( )问题",[167,169,171,173],{"key":20,"text":168,"correct":32},"技术界面",{"key":24,"text":170,"correct":22},"组织界面",{"key":27,"text":172,"correct":22},"协作界面",{"key":30,"text":174,"correct":22},"人际关系界面",{"id":176,"libraryId":5,"type":15,"typeLabel":16,"stem":177,"options":178,"answer":24,"analysis":33},937734,"（2007年真题）获取项目团队人员的基本方法中一般不包括( )。",[179,181,183,185],{"key":20,"text":180,"correct":22},"预安排",{"key":24,"text":182,"correct":32},"培训",{"key":27,"text":184,"correct":22},"商谈",{"key":30,"text":186,"correct":22},"招聘",{"id":188,"libraryId":5,"type":15,"typeLabel":16,"stem":189,"options":190,"answer":30,"analysis":33},937735,"（2013年真题）工程项目管理中的组织规模通常是指该组织的( )。",[191,193,195,197],{"key":20,"text":192,"correct":22},"办公面积",{"key":24,"text":194,"correct":22},"注册资本",{"key":27,"text":196,"correct":22},"部门数量",{"key":30,"text":198,"correct":32},"人员数量",{"id":200,"libraryId":5,"type":15,"typeLabel":16,"stem":201,"options":202,"answer":27,"analysis":33},937736,"（2011年真题）工程项目管理中的组织规模通常是指该组织( )。",[203,205,207,209],{"key":20,"text":204,"correct":22},"负责业务区域的大小",{"key":24,"text":206,"correct":22},"合同额或收入的多少",{"key":27,"text":208,"correct":32},"管辖人员数量的多少",{"key":30,"text":210,"correct":22},"项目投资额的多少",{"id":212,"libraryId":5,"type":15,"typeLabel":16,"stem":213,"options":214,"answer":27,"analysis":33},937737,"（2013年真题）工程项目管理组织中，上级管理者直接领导的下级人员数量称为( )。",[215,217,219,221],{"key":20,"text":216,"correct":22},"组织规模",{"key":24,"text":218,"correct":22},"组织结构",{"key":27,"text":220,"correct":32},"管理幅度",{"key":30,"text":222,"correct":22},"管理层次",{"id":224,"libraryId":5,"type":15,"typeLabel":16,"stem":225,"options":226,"answer":27,"analysis":33},937738,"（2010年真题）工程项目管理组织中，一名管理者直接领导多少人才能保证管理是最有效，这属于( )方面的问题。",[227,228,230,231],{"key":20,"text":216,"correct":22},{"key":24,"text":229,"correct":22},"组织构成",{"key":27,"text":220,"correct":32},{"key":30,"text":232,"correct":22},"部门设置",{"id":234,"libraryId":5,"type":15,"typeLabel":16,"stem":235,"options":236,"answer":20,"analysis":33},937739,"（2013年真题）单一项目的公司对内部进行部门设置通常采用( )。",[237,239,241,243],{"key":20,"text":238,"correct":32},"职能划分法",{"key":24,"text":240,"correct":22},"时间划分法",{"key":27,"text":242,"correct":22},"区域划分法",{"key":30,"text":244,"correct":22},"业务划分法",{"id":246,"libraryId":5,"type":15,"typeLabel":16,"stem":247,"options":248,"answer":24,"analysis":33},937740,"（2008年真题）某工程项目管理公司内设市场开发部、项目设计部、施工管理部、维修检查部，这种部门划分方法属于( )",[249,250,252,253],{"key":20,"text":244,"correct":22},{"key":24,"text":251,"correct":32},"程序划分法",{"key":27,"text":238,"correct":22},{"key":30,"text":254,"correct":22},"综合划分法",{"id":256,"libraryId":5,"type":15,"typeLabel":16,"stem":257,"options":258,"answer":20,"analysis":33},937741,"（2011年真题）把相同或相近专业的项目划入同一部门中的部门划分方法是( )。",[259,260,261,262],{"key":20,"text":244,"correct":32},{"key":24,"text":238,"correct":22},{"key":27,"text":251,"correct":22},{"key":30,"text":242,"correct":22},{"id":264,"libraryId":5,"type":15,"typeLabel":16,"stem":265,"options":266,"answer":30,"analysis":33},937742,"（2014年真题）根据职务特征模型(JCM)，能让任职者体验到工作成果责任感的核心难度是( )",[267,269,271,273],{"key":20,"text":268,"correct":22},"技能多样性",{"key":24,"text":270,"correct":22},"认为同一性",{"key":27,"text":272,"correct":22},"任务灵活性",{"key":30,"text":274,"correct":32},"工作自主性",{"id":276,"libraryId":5,"type":15,"typeLabel":16,"stem":277,"options":278,"answer":27,"analysis":33},937743,"（2017年真题）组织内各成员的努力应指向共同的目标， 相互之间应建立有效的协调， 指的是传统组织设计的( )",[279,281,283,285],{"key":20,"text":280,"correct":22},"职责原则",{"key":24,"text":282,"correct":22},"目标原则",{"key":27,"text":284,"correct":32},"协调原则",{"key":30,"text":286,"correct":22},"弹性设计原则",{"id":288,"libraryId":5,"type":15,"typeLabel":16,"stem":289,"options":290,"answer":27,"analysis":33},937744,"（2009年真题）在工程项目的组织设计中，首先强调组织整体设计目标的实现，然后进行分工，设立相应的组织单元，最后进行综合协调，这主要体现了组织设计的( )。",[291,293,295,297],{"key":20,"text":292,"correct":22},"最佳幅度与层次原则",{"key":24,"text":294,"correct":22},"目标导向原则",{"key":27,"text":296,"correct":32},"整分合原则",{"key":30,"text":298,"correct":22},"“封闭”设计原则",{"id":300,"libraryId":5,"type":15,"typeLabel":16,"stem":301,"options":302,"answer":30,"analysis":33},937745,"（2007年真题）属于矩阵式组织结构优点的是( )",[303,305,307,309],{"key":20,"text":304,"correct":22},"项目管理指令一致",{"key":24,"text":306,"correct":22},"团队成员工作目标单一",{"key":27,"text":308,"correct":22},"项目管理权力平衡容易",{"key":30,"text":310,"correct":32},"团队成员无后顾之忧",{"id":312,"libraryId":5,"type":15,"typeLabel":16,"stem":313,"options":314,"answer":24,"analysis":33},937746,"（2013年真题）关于复合式组织结构的说法，错误的是( )",[315,317,319,321],{"key":20,"text":316,"correct":22},"组织结构不受现有管理模式限制",{"key":24,"text":318,"correct":32},"组织结构内信息流较为顺畅",{"key":27,"text":320,"correct":22},"同一公司内可能有多种组织结构形式",{"key":30,"text":322,"correct":22},"同一项目可能有多种组织结构形式",{"id":324,"libraryId":5,"type":15,"typeLabel":16,"stem":325,"options":326,"answer":24,"analysis":33},937747,"（2013年真题）全职人员在项目团队中的比例达到五分之一，有专职项目经理的工程项目组织模式是( )。",[327,329,331,333],{"key":20,"text":328,"correct":22},"项目式模式",{"key":24,"text":330,"correct":32},"平衡矩阵式模式",{"key":27,"text":332,"correct":22},"强矩阵式模式",{"key":30,"text":334,"correct":22},"弱矩阵式模式",{"id":336,"libraryId":5,"type":15,"typeLabel":16,"stem":337,"options":338,"answer":24,"analysis":33},937748,"（2005年真题）处理工程项目管理组织调整中的矛盾，首先应当考虑的是( )。",[339,341,343,345],{"key":20,"text":340,"correct":22},"公司利益",{"key":24,"text":342,"correct":32},"客户利益",{"key":27,"text":344,"correct":22},"项目主管上级的意见",{"key":30,"text":346,"correct":22},"项目经理的意见",{"id":348,"libraryId":5,"type":15,"typeLabel":16,"stem":349,"options":350,"answer":20,"analysis":33},937749,"（2009年真题）团队的工作开始进入有序化状态，培养了初步的团队精神，此时的团队处于( )。",[351,353,355,357],{"key":20,"text":352,"correct":32},"规范阶段",{"key":24,"text":354,"correct":22},"表现阶段",{"key":27,"text":356,"correct":22},"形成阶段",{"key":30,"text":358,"correct":22},"磨合阶段",{"id":360,"libraryId":5,"type":15,"typeLabel":16,"stem":361,"options":362,"answer":30,"analysis":33},937750,"（2014年真题）让处于项目团队计划执行中最末端的团队成员参与团队计划的制订过程，属于团队能力开发中的( )活动",[363,365,367,369],{"key":20,"text":364,"correct":22},"改善工作环境",{"key":24,"text":366,"correct":22},"表彰与奖励",{"key":27,"text":368,"correct":22},"进行人员配合训练",{"key":30,"text":370,"correct":32},"开展团队建设性",{"id":372,"libraryId":5,"type":15,"typeLabel":16,"stem":373,"options":374,"answer":24,"analysis":33},937751,"(2012)对工程项目团队完成工作的进度与费用进行跟踪检查时，常用的管理工具是( )。",[375,377,379,381],{"key":20,"text":376,"correct":22},"直方图与决策树",{"key":24,"text":378,"correct":32},"横道图与网络图",{"key":27,"text":380,"correct":22},"网络图与鱼刺图",{"key":30,"text":382,"correct":22},"横道图与决策树",{"id":384,"libraryId":5,"type":15,"typeLabel":16,"stem":385,"options":386,"answer":27,"analysis":33},937752,"（2006年真题）下列关于工程项目人力资源管理中职责与角色关系的表述，正确的是( )",[387,389,391,393],{"key":20,"text":388,"correct":22},"职责等同于角色",{"key":24,"text":390,"correct":22},"职责与角色应该是项目团队内部人员的分工",{"key":27,"text":392,"correct":32},"职责与角色必须分配给合适的项目参与者",{"key":30,"text":394,"correct":22},"角色和职责只能安排给某一组成员",{"id":396,"libraryId":5,"type":15,"typeLabel":16,"stem":397,"options":398,"answer":27,"analysis":33},937753,"（2017年真题）采用传统组织机构图，描述项目团队成员角色与职责，以图形方式自上而下表示各种职位及其相互关系的形式是( )",[399,401,403,405],{"key":20,"text":400,"correct":22},"矩阵型",{"key":24,"text":402,"correct":22},"文本型",{"key":27,"text":404,"correct":32},"层级型",{"key":30,"text":406,"correct":22},"网络型",{"id":408,"libraryId":5,"type":15,"typeLabel":16,"stem":409,"options":410,"answer":30,"analysis":33},937754,"（2010年真题）确定和体现项目组织内各组织单元或个人之间的相互工作关系的图形是( )",[411,412,414,416],{"key":20,"text":147,"correct":22},{"key":24,"text":413,"correct":22},"线性关系图",{"key":27,"text":415,"correct":22},"横道图",{"key":30,"text":417,"correct":32},"组织关系图",{"id":419,"libraryId":5,"type":15,"typeLabel":16,"stem":420,"options":421,"answer":30,"analysis":33},937755,"（2012年真题）为使团队成员对其工作有明确的了解和把握，应对工作进行必要的说明，这在项目人力资源管理中称为( )。",[422,424,426,427],{"key":20,"text":423,"correct":22},"角色和职责安排",{"key":24,"text":425,"correct":22},"人员配备计划",{"key":27,"text":174,"correct":22},{"key":30,"text":428,"correct":32},"工作描述",{"id":430,"libraryId":5,"type":15,"typeLabel":16,"stem":431,"options":432,"answer":27,"analysis":33},937756,"（2014年真题）项目团队的一些特殊人员必须按照委托方要求来设定岗位，这种人员配备方式属于( )",[433,435,437,438],{"key":20,"text":434,"correct":22},"内部招聘",{"key":24,"text":436,"correct":22},"外部招聘",{"key":27,"text":180,"correct":32},{"key":30,"text":184,"correct":22},{"id":440,"libraryId":5,"type":15,"typeLabel":16,"stem":441,"options":442,"answer":20,"analysis":33},937757,"（2016年真题）—般情况下，最高层管理人员的管理幅度( )为宜",[443,445,447,449],{"key":20,"text":444,"correct":32},"4?8",{"key":24,"text":446,"correct":22},"8?15",{"key":27,"text":448,"correct":22},"15?22",{"key":30,"text":450,"correct":22},"20?30",{"id":452,"libraryId":5,"type":15,"typeLabel":16,"stem":453,"options":454,"answer":24,"analysis":33},937758,"（2012年真题）通常情况下，最高层管理人员和基层管理人员的分别以( )为宜",[455,457,459,461],{"key":20,"text":456,"correct":22},"3～5人和8～10人",{"key":24,"text":458,"correct":32},"4～8人和8～15人",{"key":27,"text":460,"correct":22},"3～5人和6～8人",{"key":30,"text":462,"correct":22},"2～5人和5～7人",{"id":464,"libraryId":5,"type":15,"typeLabel":16,"stem":465,"options":466,"answer":24,"analysis":33},937759,"（2012年真题）某公司为降低组织运营成本，应采取( )的方法。",[467,469,471,473],{"key":20,"text":468,"correct":22},"减少管理幅度、增加管理层次",{"key":24,"text":470,"correct":32},"减少管理层次、增加管理幅度",{"key":27,"text":472,"correct":22},"增加管理幅度、增加管理层次",{"key":30,"text":474,"correct":22},"减少管理层次、减少管理幅度",{"id":476,"libraryId":5,"type":15,"typeLabel":16,"stem":477,"options":478,"answer":24,"analysis":33},937760,"（2011年真题）在组织规模不变的情况下，为缩小组织运营成本，可以采用( )的做法。",[479,481,483,484],{"key":20,"text":480,"correct":22},"增加管理层次、减少管理幅度",{"key":24,"text":482,"correct":32},"增加管理幅度、减少管理层次",{"key":27,"text":472,"correct":22},{"key":30,"text":474,"correct":22},{"id":486,"libraryId":5,"type":15,"typeLabel":16,"stem":487,"options":488,"answer":27,"analysis":33},937761,"（2011年真题）根据美国洛克希德公司提出的管理幅度定量分析方法，当管理职能( )时，管理幅度最小",[489,491,493,495],{"key":20,"text":490,"correct":22},"完全相同",{"key":24,"text":492,"correct":22},"基本相同",{"key":27,"text":494,"correct":32},"根本不同",{"key":30,"text":496,"correct":22},"基本不同",{"id":498,"libraryId":5,"type":15,"typeLabel":16,"stem":499,"options":500,"answer":30,"analysis":33},937762,"（2010年真题）根据美国洛克希德公司的管理幅度定量方法，在相同条件下，对管理幅度影响最大的是( )因素",[501,503,505,507],{"key":20,"text":502,"correct":22},"地点相近性",{"key":24,"text":504,"correct":22},"职能相似性",{"key":27,"text":506,"correct":22},"职能复杂性",{"key":30,"text":508,"correct":32},"直接监督需要程度",{"id":510,"libraryId":5,"type":15,"typeLabel":16,"stem":511,"options":512,"answer":27,"analysis":33},937763,"（2013年真题）项目管理组织中的管理层次是指( )。",[513,515,517,519],{"key":20,"text":514,"correct":22},"最高管理者的学历",{"key":24,"text":516,"correct":22},"管理人员的职称层次",{"key":27,"text":518,"correct":32},"管理分级的层次",{"key":30,"text":520,"correct":22},"管理者的行政级别层次",{"id":522,"libraryId":5,"type":15,"typeLabel":16,"stem":523,"options":524,"answer":27,"analysis":33},937764,"（2014年真题）对职能分工清楚的管理组织而言，直接调动和安排项目活动、组织落实项目计划的阶层是( )",[525,527,529,531],{"key":20,"text":526,"correct":22},"决策层",{"key":24,"text":528,"correct":22},"协调层",{"key":27,"text":530,"correct":32},"执行层",{"key":30,"text":532,"correct":22},"操作层",{"id":534,"libraryId":5,"type":15,"typeLabel":16,"stem":535,"options":536,"answer":27,"analysis":33},937765,"（2006年真题）工程项目管理组织一般分为四个层次，按从上到下顺序第三个层次是( )。",[537,538,539,540],{"key":20,"text":526,"correct":22},{"key":24,"text":532,"correct":22},{"key":27,"text":530,"correct":32},{"key":30,"text":528,"correct":22},{"id":542,"libraryId":5,"type":15,"typeLabel":16,"stem":543,"options":544,"answer":24,"analysis":33},937766,"（2016年真题）下列关于管理层次与管理幅度的关系的说法错误的是( )。",[545,547,549,551],{"key":20,"text":546,"correct":22},"—般来说，管理层次与管理跨度相互矛盾",{"key":24,"text":548,"correct":32},"管理跨度与管理层次成正比关系",{"key":27,"text":550,"correct":22},"在组织中人数一定的情况下，管理层次越多，管理幅度越小",{"key":30,"text":552,"correct":22},"要使决策和管理效率高效、快捷，必须平衡管理层次与管理跨度的关系",{"id":554,"libraryId":5,"type":15,"typeLabel":16,"stem":555,"options":556,"answer":27,"analysis":33},937767,"（2009年真题）下列建立项目管理组织的步骤，正确的先后顺序是( )。①确定项目工作内容；②确定合理的项目目标；③组织结构设计；④确定组织目标和组织工作内容。",[557,559,561,563],{"key":20,"text":558,"correct":22},"①－②－③－④",{"key":24,"text":560,"correct":22},"②－①－③－④",{"key":27,"text":562,"correct":32},"②－①－④－③",{"key":30,"text":564,"correct":22},"①－②－④－③",{"id":566,"libraryId":5,"type":15,"typeLabel":16,"stem":567,"options":568,"answer":20,"analysis":33},937768,"（2016年真题）目前国内咨询公司在咨询项目中应用最为广泛的项目组织的基本形式是( )",[569,571,573,575],{"key":20,"text":570,"correct":32},"职能式组织形式",{"key":24,"text":572,"correct":22},"项目式组织形式",{"key":27,"text":574,"correct":22},"矩阵式组织形式",{"key":30,"text":576,"correct":22},"复合式组织形式",{"id":578,"libraryId":5,"type":15,"typeLabel":16,"stem":579,"options":580,"answer":27,"analysis":33},937769,"（2005年真题）某咨询公司就一大型通信企业规划项目做出如下安排：公司副总经理牵头，有关技术分析工作由通信项目部负责，有关财务分析工作由经济部负责，其余工作也分到相应部门中去。该公司就该咨询工作采取的组织形式是( )",[581,583,585,587],{"key":20,"text":582,"correct":22},"矩阵式",{"key":24,"text":584,"correct":22},"复合式",{"key":27,"text":586,"correct":32},"职能式",{"key":30,"text":588,"correct":22},"项目式",{"id":590,"libraryId":5,"type":15,"typeLabel":16,"stem":591,"options":592,"answer":27,"analysis":33},937770,"（2006年真题）根据项目专业特点，将项目直接安排到公司某一部门内进行，这属于 ( )组织形式",[593,594,595,596],{"key":20,"text":584,"correct":22},{"key":24,"text":588,"correct":22},{"key":27,"text":586,"correct":32},{"key":30,"text":582,"correct":22},[598,601,604,607,610,613],{"id":15,"name":599,"category":7,"favorite":600},"领导干部任职前廉政法规知识测试题",92,{"id":602,"name":603,"category":7,"favorite":15},595,"建筑结构与设备",{"id":605,"name":606,"category":7,"favorite":15},715,"招标采购专业知识与法律法规",{"id":608,"name":609,"category":7,"favorite":15},848,"市政方向-通用基础",{"id":611,"name":612,"category":7,"favorite":8},534,"BIM工程师",{"id":614,"name":612,"category":7,"favorite":8},535]