[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939650":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939650,606,1,"单选题","工程项目过程控制中，一般将项目过程分为（ ）两大类。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目决策过程与项目实施过程",false,{"key":16,"text":17,"correct":14},"B","项目设计过程与项目管理过程",{"key":19,"text":20,"correct":21},"C","产品创造过程与项目管理过程",true,{"key":23,"text":24,"correct":14},"D","项目计划过程与项目实施过程","本题考查的是工程项目管理的基本原理。项目过程分为两大类：一类是创造项目产品的过程；另一类是项目管理过程。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]