[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939648":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939648,606,1,"单选题","对存在于项目中的各种技术界面和组织界面进行管理并做好记录的工作，属于过程管理中的（ ）过程。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","检查",false,{"key":16,"text":17,"correct":14},"B","处理",{"key":19,"text":20,"correct":21},"C","实施",true,{"key":23,"text":24,"correct":14},"D","计划","本题考查的是工程项目管理的基本原理。实施过程就是资源投入到成果实现的过程，主要就是协调人力和其他资源以执行工程项目计划。在这个过程中，工程项目管理团队必须对存在于工程项目中的各种技术和组织界面进行管理；并做好记录，包括人力和其他资源的投入、活动过程、成果的评审、确认等记录。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]