[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939638":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939638,606,2,"多选题","工程项目管理处于多种因素构成的复杂环境中，必须考虑（ ）等多方面的影响。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","上级组织",true,{"key":16,"text":17,"correct":18},"B","竞争对手",false,{"key":20,"text":21,"correct":14},"C","社会经济、文化、政治、法律",{"key":23,"text":24,"correct":18},"D","项目管理论的发展",{"key":26,"text":27,"correct":14},"E","标准规范和规程的约束","ACE","本题考查的是工程项目管理的含义。选项BD属于项目日常活动。任何一个工程项目管理团队仅仅对工程项目本身的日常活动进行管理是远远不够的，必须考虑多方面的影响。主要有如下因素：（1）上级组织的影响；（2）社会、经济、文化、政治和法律等方面的影响；（3）标准、规范和规程的约束。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]