[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939636":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939636,606,1,"单选题","社会公众对垃圾处理建设项目的要求和期望不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","无污染",false,{"key":16,"text":17,"correct":18},"B","收益高",true,{"key":20,"text":21,"correct":14},"C","有社会效益",{"key":23,"text":24,"correct":14},"D","服务优良","本题考查的是工程项目的主要利益相关方及其要求和期望。社会公众要求和期望：工程建设期无社会风险，无污染及公害，在工程项目运行期内对外部环境不产生有害的影响，工程项目有社会效益，产出品或提供的服务质量优良、价格合理。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]