[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939635":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939635,606,1,"单选题","工程项目主要利害关系者中，内部各部门的要求和期望是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","松弛的工作进度表、合理的报酬",false,{"key":16,"text":17,"correct":14},"B","迅速批准开工",{"key":19,"text":20,"correct":21},"C","松弛的工作进度表，足够的信息、人力和物资资源",true,{"key":23,"text":24,"correct":14},"D","按质量要求，按时或提前形成综合生产力","本题考查的是工程项目的主要利益相关方及其要求和期望。内部各部门要求和期望：松弛的工作进度表，优良的工作环境，有足够的信息资源、人力资源和物资资源。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]