[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939634":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939634,606,1,"单选题","承包商对工程项目的要求和期望是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投资少，质量合格",false,{"key":16,"text":17,"correct":18},"B","利润优厚，及时付款",true,{"key":20,"text":21,"correct":14},"C","质量合格，运营正常",{"key":23,"text":24,"correct":14},"D","贷款安全，保证进度","本题考查的是工程项目的主要利益相关方及其要求和期望。承包商要求和期望：优厚的利润，及时提供施工图纸，最小限度的变动，原材料和设备及时送达工地，公众无抱怨，可自己选择施工方法，不受其他承包商的干扰，按时支付工程进度款，迅速批准开工，及时提供服务。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]