[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939631":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939631,606,2,"多选题","工程项目具有( )等特点，决定了其过程控制的动态特征。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","一次性",true,{"key":16,"text":17,"correct":14},"B","固定性",{"key":19,"text":20,"correct":14},"C","诸多因素带有不确定性",{"key":22,"text":23,"correct":24},"D","整体性",false,{"key":26,"text":27,"correct":24},"E","独特性","ABC","工程项目具有一次性、固定性、诸多因素带有不确定性等特点，决定了其过程控制的动态特征。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]