[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939619":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939619,606,1,"单选题","投资少、利益大、时间短、质量合格，这是（ ）对工程项目的要求和期望。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目业主",true,{"key":16,"text":17,"correct":18},"B","咨询机构",false,{"key":20,"text":21,"correct":18},"C","金融机构",{"key":23,"text":24,"correct":18},"D","政府部门","本题考查的是工程项目的主要利益相关方及其要求和期望。业主的要求和期望：投资少、利益大、时间短、质量合格。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]