[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939617":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939617,606,1,"单选题","工程项目征地及建设条件的准备是（ ）的具体工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程项目前期阶段",false,{"key":16,"text":17,"correct":18},"B","工程项目准备阶段",true,{"key":20,"text":21,"correct":14},"C","工程项目实施阶段",{"key":23,"text":24,"correct":14},"D","工程项目投产运营阶段","本题考查的是工程项目各阶段主要工作内容。工程项目准备阶段的主要工作包括：工程项目的初步设计和施工图设计，工程项目征地及建设条件的准备，工程招标并与承包人签订承包合同，获得相关工程建设行政许可，货物采购等。本阶段是战略决策的具体化，在很大程度上决定了工程项目实施的成败及能否高效率地达到预期目标。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]