[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939614":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939614,606,1,"单选题","下列有关工程项目周期阶段的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程项目准备阶段的主要任务是对工程项目投资的必要性.可行性进行科学论证",false,{"key":16,"text":17,"correct":14},"B","工程项目准备阶段投入少，却对工程项目的战略方向起着决定性的作用",{"key":19,"text":20,"correct":21},"C","工程项目试生产正常并经业主验收后，工程项目实施阶段即告结束",true,{"key":23,"text":24,"correct":14},"D","工程项目实施阶段包括项目的保修和回访","本题考查的是工程项目各阶段主要工作内容。选项 A、B 的表述为前期阶段，选项 D 错误，在项目的投产运营期间的主要工作有保修、回访和相关的后续服务及项目后评价。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]