[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939613":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939613,606,1,"单选题","下列关于工程项目主要利害关系者，对工程项目的要求和期望表达错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","政府部门要求工程项目与整个国家.政策。立法相一致",false,{"key":16,"text":17,"correct":14},"B","项目业主期望投资少，利益高，时间段，质量合格",{"key":19,"text":20,"correct":21},"C","金融机构要求贷款安全，按预定日期支付贷款，项目能提供较低的回报",true,{"key":23,"text":24,"correct":14},"D","社会公众期望工程建设无社会风险，无污染及公害","本题考查的是工程项目的主要利益相关方及其要求和期望。金融机构的要求和期望是贷款安全，按预定日期支付，项目能提供较高的回报，按期清偿债务。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]