[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939612":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939612,606,1,"单选题","下列关于工程项目目标的说法，不正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程项目目标是一种层次结构",false,{"key":16,"text":17,"correct":14},"B","工程项目目标系统可以采用 WBS 建立",{"key":19,"text":20,"correct":14},"C","项目目标系统至少由三个层次构成",{"key":22,"text":23,"correct":24},"D","工程项目目标系统建立的第一步是识别需求",true,"本题考查的是工程项目的系统管理原理。工程项目目标系统建立的第一步是工程项目构思。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]