[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939608":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939608,606,2,"多选题","工程项目的主要利益相关方的要求和期望，需要从以下( )层面来理解。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","工程项目具有哪些利益相关方",true,{"key":16,"text":17,"correct":14},"B","利益相关方有哪些方面的要求和期望",{"key":19,"text":20,"correct":14},"C","利益相关方每一个方面的具体要求和期望是什么",{"key":22,"text":23,"correct":14},"D","利益相关方要求和期望之间具有什么样的冲突",{"key":25,"text":26,"correct":27},"E","如何协调利益相关方之间的冲突，并满足或超出他们的所有要求及期望",false,"ABCD","工程项目的主要利益相关方的要求和期望，至少需要从以下五个层面来理解：一是工程项目具有哪些利益相关方；二是他们具有哪些方面的要求和期望；三是他们每一个方面的具体要求和期望是什么；四是这些要求和期望具有什么样的冲突；五是如何运用各种知识、技能、手段和方法去协调这些冲突，并满足或超出他们的合理要求及期望。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]