[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939607":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939607,606,2,"多选题","下列关于工程项目管理的说法，正确的有( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","项目备案属于工程项目外部管理",true,{"key":16,"text":17,"correct":14},"B","内部管理主要是通过建立和运行科学的管理体系实现",{"key":19,"text":20,"correct":14},"C","业主方的项目管理是工程项目管理的核心",{"key":22,"text":23,"correct":24},"D","内部管理具有强制约束作用",false,{"key":26,"text":27,"correct":14},"E","工程项目管理的环境分为内部环境和外部环境","ABCE","工程项目内部管理是指项目业主、工程承包单位和项目管理服务单位，对工程项目投资建设活动实施的管理。工程项目外部管理主要是指各级政府部门按职能分工，对工程项目进行的行政管理",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]